Torsdag 15 Maj | 20:48:06 Europe / Stockholm

Bifogade filer

Prenumeration

Kalender

Est. tid*
2026-02-12 13:00 Bokslutskommuniké 2025
2025-11-13 13:00 Kvartalsrapport 2025-Q3
2025-08-25 13:00 Kvartalsrapport 2025-Q2
2025-05-23 N/A X-dag ordinarie utdelning GIGA 0.00 SEK
2025-05-22 N/A Årsstämma
2025-05-15 13:00 Kvartalsrapport 2025-Q1
2025-02-19 - Bokslutskommuniké 2024
2024-11-14 - Kvartalsrapport 2024-Q3
2024-08-26 - Kvartalsrapport 2024-Q2
2024-06-13 - X-dag ordinarie utdelning GIGA 0.00 SEK
2024-06-12 - Årsstämma
2024-05-16 - Kvartalsrapport 2024-Q1
2024-02-20 - Bokslutskommuniké 2023
2023-11-16 - Kvartalsrapport 2023-Q3
2023-08-10 - Kvartalsrapport 2023-Q2
2023-06-29 - Årsstämma
2023-06-16 - X-dag ordinarie utdelning GIGA 0.00 SEK
2023-05-10 - Kvartalsrapport 2023-Q1
2023-02-23 - Bokslutskommuniké 2022
2022-11-01 - Kvartalsrapport 2022-Q3
2022-08-23 - Kvartalsrapport 2022-Q2
2022-05-20 - X-dag ordinarie utdelning GIGA 0.00 SEK
2022-05-19 - Årsstämma
2022-05-18 - Kvartalsrapport 2022-Q1
2022-02-24 - Bokslutskommuniké 2021
2021-11-30 - Kvartalsrapport 2021-Q3

Beskrivning

LandSverige
ListaFirst North Stockholm
SektorEnergi & Miljö
IndustriEnergikällor
Gigasun är verksamt inom energisektorn. Bolaget är en energiproducent av el som finansierar, äger och driver takmonterade solcellsanläggningar i Kina. Elen som produceras av bolaget säljs främst till fastighetsägarna. Bolaget är primärt verksamma inom den kinesiska marknaden. Bolaget gick tidigare under namnet Advanced SolTech Sweden. Bolaget grundades 2014 och har sitt huvudkontor i Stockholm.
2025-05-15 13:00:00

During the quarter, the company's 200 (187) solar PV installations produced a total of 55.0 (46.5) million kWh, an increase of 18.4% compared to the previous year. Through this, we have reduced carbon dioxide emissions by approximately 27,000 (23,000) tons. New contracts for an additional 15.6 (4.1) MW were signed during the quarter. Financially, the quarter showed sales of SEK 46.3 (40.5) million and a loss after financial items and tax of SEK -20.9 (-15.9) million. This quarter, the currency effect was SEK -1.8 (0.8) million.

The quarter, in short
January 1st – March 31st

  • The company installed a total of 0.0 (4.5) MW of roof-based solar PV installations and had 340.1 (286.3) MW installed capacity at the end of the quarter.
  • 55.0 (46.5) million kWh were produced which reduced carbon dioxide related emissions by approximately 27,000 (23,000) tons.
  • At the end of the quarter, the company had 54.4 (43.0) MW in subscribed orders, as well as projects in the pipeline of 142.4 (131.1) MW.
  • The company signed 4 (3) contracts amounting to a total installed capacity of 15.6 (4.1) MW.
  • The interest rate on leasing loans corresponding to SEK 515 million with JS Leasing was reduced by up to 70 basis points due to a lower reference rate, which lowers interest costs on affected loans by approximately SEK 3.1 million on an annual basis.

 The quarter, in numbers
January 1st – March 31st

  • Revenues (sales of electricity and subsidies) amounted to SEK 46.3 (40.5) million.
  • Net sales (sales of electricity to customers and Grid) amounted to SEK 38.2 (33.8) million.
  • Other operating income (subsidies and other) amounted to SEK 8.1 (6.7) million.
  • Operating expenses amounted to SEK 43.0 (36.3) million
  • Operating profit for the quarter amounted to SEK 3.3 (4.2) million.
  • Interest expenses and similar charges amounted to SEK 22.5 (21.0) million.
  • Loss for the quarter after financial items and tax amounted to SEK -20.9 (-15.9) million and was impacted by a currency effect of SEK -1.8 (0.8) million. Adjusted for the currency effect, loss for the quarter amounted to SEK -19.1 (-16.7) million.
  • Total cash flow for the quarter amounted to SEK -17.0 (4.4) million.
  • Earnings per share before dilution amounted to SEK -0.37 (-0.28).
  • The number of employees at the end of the period was 22 (19).

Significant events after the end of the period

  • The company signed 1 contract amounting to an installed capacity of 1.0 MW.
  • As of May 1, 2025, most of the electricity from new solar PV installations must be sold to an end customer. This is the most common customer arrangement for Gigasun, and we therefore do not expect this to have any significant impact going forward. Due to this policy change, it has been a priority to complete projects where all electricity is to be sold to the grid.
  • The company has installed 8 new solar PV installations with a total installed capacity of 36.9 MW, of which 7 projects sell 100% of their production to the grid. Total installed capacity at the time of this report is 377.0 MW.