Tisdag 29 April | 14:25:05 Europe / Stockholm

Prenumeration

Kalender

Est. tid*
2025-11-19 08:00 Kvartalsrapport 2025-Q3
2025-08-20 08:00 Kvartalsrapport 2025-Q2
2025-05-28 08:00 Kvartalsrapport 2025-Q1
2025-05-09 N/A X-dag ordinarie utdelning HEXI 0.00 SEK
2025-05-07 N/A Årsstämma
2025-02-19 - Bokslutskommuniké 2024
2024-11-29 - Kvartalsrapport 2024-Q3
2024-08-21 - Kvartalsrapport 2024-Q2
2024-05-29 - Kvartalsrapport 2024-Q1
2024-05-17 - X-dag ordinarie utdelning HEXI 0.00 SEK
2024-02-21 - Bokslutskommuniké 2023
2023-11-17 - Kvartalsrapport 2023-Q3
2023-08-31 - Kvartalsrapport 2023-Q2
2023-05-31 - Kvartalsrapport 2023-Q1
2023-05-05 - X-dag ordinarie utdelning HEXI 0.00 SEK
2023-02-23 - Bokslutskommuniké 2022
2022-12-15 - Extra Bolagsstämma 2022
2022-11-09 - Kvartalsrapport 2022-Q3
2022-08-18 - Kvartalsrapport 2022-Q2
2022-05-13 - X-dag ordinarie utdelning HEXI 0.00 SEK
2022-05-12 - Årsstämma
2022-05-11 - Kvartalsrapport 2022-Q1
2022-02-23 - Bokslutskommuniké 2021
2021-11-16 - Kvartalsrapport 2021-Q3
2021-08-17 - Kvartalsrapport 2021-Q2

Beskrivning

LandSverige
ListaFirst North Stockholm
SektorEnergi & Miljö
IndustriEnergikällor
Hexicon är en projektutvecklare inom flytande vind som öppnar upp nya marknader i länder med djupt vatten. Bolaget är också teknikleverantör med TwinWind, en patenterad flytande vinddesign. Tekniken möjliggör utökat nyttjande av global vindkraft och kan därmed bidra till ökad tillgång till förnyelsebar energi. Hexicon verkar på flera marknader i Europa, Afrika, Asien och Nordamerika.
2023-01-19 13:00:00

Italian TSO, Terna SpA, has granted six of Hexicon’s seven wind power sites connection to the national grid. The six sites encompass a total combined capacity of 7,100 MW. Permit for the remaining site is still in process.

Hexicon, operating in Italy through its joint venture AvenHexicon, now has a portfolio of seven development sites for floating wind along the coasts of Sardinia, Sicily and Puglia. Grid connections were applied for in 2022 and Terna has now issued the technical solution to connect six of the seven locations to the national grid - a total combined capacity of 7,100 MW. 
 
The interconnection permit, also called STMG, is a preliminary agreement from Terna to provide interconnection capacity. It provides a commitment from the TSO to make the necessary capacity available to be connected to the grid and is a mandatory step to receive the main authorization (the so called “Autorizzazione Unica” or “AU”) to build and operate an offshore wind farm. The grid connection solutions are issued for six offshore wind farms under development off the coasts of Sardinia, Sicily and the mainland, in Puglia. The grid connection application for the remaining wind site is currently being processed and is expected to come through shortly. 

“The progress is moving at record speed, which speaks for Italy's ambition to develop renewables in the country. Having the grid connection ready is yet another milestone passed, and one which significantly increases the value of each project,”, says Alberto Dalla Rosa, CEO at AvenHexicon. 
 
The Italian government signaled early on an ambition to take measures to speed up the processes for renewable energy projects, to faster cut dependence on Russian gas. With a vast coastline and excellent wind resources, especially in the deep waters of the Mediterranean Sea, Italy has a strong potential for floating wind. GWEC has highlighted the country as one of the top five emerging markets for offshore wind. The country is aiming to generate 55% of its total electricity generation from renewables by 2030.