Bravida Holding AB: Bravida to install in Svenska kraftnät's Citylink project for approximately SEK 157 million
Bravida has signed an agreement with JV Hochtief Implenia HB for installations as part of Svenska kraftnät's Citylink project in Stockholm. The assignment includes the installation and commissioning of electrical, heating and plumbing, ventilation and control systems.
Citylink is part of Svenska kraftnät's initiative to future-proof the electricity supply in the Stockholm region by connecting the power grid between northern and southern Stockholm. Bravida's work will be carried out along the 13-kilometre tunnel section between Anneberg and Skanstull, where the deepest section is located approximately 100 metres underground.
"Bravida's Citylink assignment strengthens our leading position in large, complex installation projects within critical infrastructure. Projects like this require extensive experience, specialist expertise and strong collaboration skills," comments Lars Täuber, Head of Division Sweden at Bravida.
Work began in October 2026 and is expected to be completed in June 2028. The order was registered in Bravida's order intake in the third quarter of 2026.
For further information, please contact:
Liselotte Stray
Head of Group Communications
liselotte.stray@bravida.se
+46 76 852 38 11