14:07:06 Europe / Stockholm

Bifogade filer

Kurs & Likviditet

Kursutveckling och likviditet under dagen för detta pressmeddelande

Kalender

2025-02-27 Bokslutskommuniké 2024
2024-08-22 Kvartalsrapport 2024-Q2
2024-05-22 Årsstämma 2024
2024-04-25 X-dag ordinarie utdelning MINEST 0.00 SEK
2024-03-14 Extra Bolagsstämma 2024
2024-03-07 Bokslutskommuniké 2023
2023-08-17 Kvartalsrapport 2023-Q2
2023-06-08 X-dag ordinarie utdelning MINEST 0.00 SEK
2023-06-07 Årsstämma 2023
2023-02-24 Bokslutskommuniké 2022
2023-02-20 Extra Bolagsstämma 2022
2022-08-18 Kvartalsrapport 2022-Q2
2022-06-09 X-dag ordinarie utdelning MINEST 0.00 SEK
2022-06-08 Årsstämma 2022
2022-03-17 Bokslutskommuniké 2021
2021-08-19 Kvartalsrapport 2021-Q2
2021-06-03 X-dag ordinarie utdelning MINEST 0.00 SEK
2021-06-02 Årsstämma 2021
2021-03-18 Bokslutskommuniké 2020
2020-08-20 Kvartalsrapport 2020-Q2
2020-06-29 Årsstämma 2020
2020-06-10 X-dag ordinarie utdelning MINEST 0.00 SEK
2020-03-19 Bokslutskommuniké 2019
2019-08-22 Kvartalsrapport 2019-Q2
2019-06-05 X-dag ordinarie utdelning MINEST 0.00 SEK
2019-06-04 Årsstämma 2019
2019-03-28 Bokslutskommuniké 2018
2018-11-15 15-10 2018-Q3
2018-08-30 Kvartalsrapport 2018-Q2
2018-06-07 X-dag ordinarie utdelning MINEST 0.00 SEK
2018-06-05 Årsstämma 2018
2018-03-29 Bokslutskommuniké 2017
2018-01-24 Extra Bolagsstämma 2017
2017-08-17 Kvartalsrapport 2017-Q2
2017-06-09 X-dag ordinarie utdelning MINEST 0.00 SEK
2017-06-08 Årsstämma 2017
2017-03-29 Bokslutskommuniké 2016
2016-11-11 Kvartalsrapport 2016-Q3
2016-08-26 Kvartalsrapport 2016-Q2
2016-06-16 X-dag ordinarie utdelning MINEST 0.00 SEK
2016-06-15 Årsstämma 2016
2016-05-16 Kvartalsrapport 2016-Q1
2016-03-31 Bokslutskommuniké 2015
2015-10-30 Kvartalsrapport 2015-Q3

Beskrivning

LandSverige
ListaFirst North Stockholm
SektorEnergi & Miljö
IndustriEnergikällor
Minesto är verksamt inom förnybar energi. Bolagets egenutvecklade teknik används för att producera el från tidvatten- och havsströmmar och riktar sig mot elbolag, andra kraftproducenter samt projektutvecklare. Verksamheten bedrivs idag främst i Europa och Asien. Bolaget grundades 2007 som en avknoppning från Saab och har sitt huvudkontor i Göteborg.
2024-05-22 10:10:42

In today's presentation at the AGM (Annual General Meeting), Minesto shares Dragon Class performance data based on accumulated analysis of Dragon 4 power production curve and verified simulation modelling. The data plays a key role in third-party technical feasibility evaluations and in calculating yearly yields for investment proposals at specific site locations.

The power-curve data show power generation at given tidal current speeds and constitutes a good performance measure of how capable the Dragon Class technology is in converting the kinetic energy in the flowing ocean to electric power.

The data presented today explains the importance of matching the right powerplant (Dragon) configuration (modularity) with specific site conditions (e.g. ocean flow conditions) to optimize output at a given tidal site.

Four data sets are presented in the attached graph.
  • First (D4 simulated) a simulation curve of the actual D4-system that has been tested since 2022. This curve is based on our in-house CFD (Computational Fluid Dynamics) simulation model.
  • Second (D4 achieved) the actual power curve based on testing is plotted indicating that our simulation modelling has high accuracy.
  • Third (D4-X wing) show how an extension of the wing (from approx. 5 to 6 metres) with the same power-take off system (100kW) move the power-curve "to the left" and thus provides significantly more power at lower flows.
  • Fourth (D4-X 200kW) show the simulated curve of an upgraded PTO (Power Take Off) with a 200kW generator and the larger wing.

The fourth curve is the performance specification that Minesto today can offer customers for installations of smaller powerplants (100-200kW for e.g. a Microgrid installations) at medium flow sites and the third curve show a system for a low flow site.

There are site-specific and technical limitations explaining the shape of the actual power curve. For example, the strength of the anchoring system and the rated power of the generator limit power production in the higher flow range. The full interpretation of power conversion performance is proprietary information only shared selectively with commercial partners under NDA.

The data from the first three-month test-phase of the larger system Dragon 12 (which is a scale-up of the D4) is as expected on-par with the presented D4 data. The Dragon 12 testing is following a stepwise ramp-up program towards optimum flight trajectories and control system settings.

"Based on actual and simulated performance data from both the D4 and the recently installed larger D12 we conclude that the technology is ready for the first Dragon Farms as well as microgrid installations. Equally important, we now have the right tools and capability to optimize the size and configuration of Dragons for specific sites. We also believe that the accumulated test data and documentation on Dragon Class technology makes it ready for third party technical evaluations by commercial actors" said Dr Martin Edlund, CEO of Minesto.

Information: The CEO presentation from today's AGM will be available in Minesto's official after the event.