Måndag 6 Januari | 21:13:49 Europe / Stockholm

Bifogade filer

Kalender

Tid*
2025-11-19 07:00 Kvartalsrapport 2025-Q3
2025-08-20 07:00 Kvartalsrapport 2025-Q2
2025-05-21 07:00 Kvartalsrapport 2025-Q1
2025-05-20 N/A Årsstämma
2025-02-27 17:00 Bokslutskommuniké 2024
2024-11-12 - Kvartalsrapport 2024-Q3
2024-08-21 - Kvartalsrapport 2024-Q2
2024-06-26 - Årsstämma
2024-05-22 - Kvartalsrapport 2024-Q1
2024-05-16 - X-dag ordinarie utdelning ENERG 0.00 NOK
2024-03-07 - Bokslutskommuniké 2023
2023-11-10 - Kvartalsrapport 2023-Q3
2023-08-23 - Kvartalsrapport 2023-Q2
2023-06-19 - Årsstämma
2023-05-16 - Kvartalsrapport 2023-Q1
2023-05-16 - X-dag ordinarie utdelning ENERG 0.00 NOK
2023-03-07 - Bokslutskommuniké 2022
2023-01-27 - Extra Bolagsstämma 2023

Beskrivning

LandNorge
ListaEuronext Growth Oslo
SektorEnergi & Miljö
IndustriEnergikällor
Energeia är verksamma inom energisektorn. Bolagets affärsverksamhet är inriktad mot produktion och distribution av förnybar energi via solkraftverk. Produktionen sker via egna anläggningar i Europa där kunderna består av både privata kunder, samt små- och medelstora företagskunder inom varierande sektorer. Bolaget grundades 2010 och har sitt huvudkontor i Oslo, Norge.
2024-08-21 07:00:00
Main events in the first half year 2024

Solar electricity production first half 2024 was 5 767 MWh, 12 per cent below
budget. Expected full-year 2024 production is in the range 11 000 to 11 500 MWh.
The reason for lower production is that Netherlands experienced record breaking
rainfall in the first half 2024, 60 per cent higher than normal with
consequential cloud cover.

First half EBITDA was NOK 0.9 million, while Q2 2024 EBITDA was NOK 4.5 million.
First half EBIT came in at a loss of NOK 6.1 million, while Q2 2024 EBIT was
positive with NOK 1 million.

Dutch operations delivered a positive EBITDA of NOK 5.5 million, Italy and
Singapore had an EBITDA NOK 0.4 million, while Norway had an EBITDA loss of NOK
4.7 million mainly related to Norwegian project development costs.

Energeia delivered the concession application for the Seval Skog power plant to
NVE on 4 March. NVE has started the application approval procedure and the next
step is the ending of the public hearing period on 12 September.

YTD 2024 Energeia has delivered notification for 370 MWdc of solar PV power
plants projects in Norway to NVE. At current Energeia has 8 projects
representing 574 MWdc in process with NVE. Energeia has received grid
reservation for 4 power plants representing 195 MWac, equivalent to 44 per cent
of total grid reservations allocated to solar PV power plants in Norway. In
addition, 3 power plants representing 272 MWac have received placement in the
grid connection queue awaiting grid capacity, in total 467 MWac.

Net cash flow in the first half year was negative with NOK 3.8 million,
decreasing Group cash position to NOK 27 million at the end of the period.

Norwegian solar power plant concession process takes much longer than originally
anticipated by NVE in 2021/2022. In addition, access and availability of grid
connection has become a bottleneck in development of power plants in Norway.
This has lead to a 18 to 24 month delay in execution of Norwegian projects from
original plan. Energeia's Dutch operations generates a positive cash flow,
however not sufficient to fully support current Norwegian development costs.
Consequently, Energeia will need to secure additional liquidity to support
Norway project development at the current phase going forward.


For further information, please contact:

CEO, Viktor Jakobsen, email: viktor@energeia.no and telephone: +47 916 11 009
Deputy CEO, Jarl Egil Markussen, email: jarl@energeia.no and telephone: +47 480
23 214


This information is subject to the disclosure requirements pursuant to Section
5-12 of the Norwegian Securities Trading Act.