Lördag 15 Augusti | 00:40:03 Europe / Stockholm
Est. tid*
2026-09-23 07:00 Kvartalsrapport 2026-Q2
2026-05-20 - X-dag ordinarie utdelning ENERG 0.00 NOK
2026-05-19 - Årsstämma
2026-04-28 - Bokslutskommuniké 2025
2025-12-02 - Split ENERG 250:1
2025-11-10 - Extra Bolagsstämma 2025
2025-09-08 - Kvartalsrapport 2025-Q2
2025-06-27 - Årsstämma
2025-06-18 - X-dag ordinarie utdelning ENERG 0.00 NOK
2025-05-16 - Extra Bolagsstämma 2024
2025-05-14 - Bokslutskommuniké 2024
2024-11-12 - Kvartalsrapport 2024-Q3
2024-08-21 - Kvartalsrapport 2024-Q2
2024-06-26 - Årsstämma
2024-05-22 - Kvartalsrapport 2024-Q1
2024-05-16 - X-dag ordinarie utdelning ENERG 0.00 NOK
2024-03-07 - Bokslutskommuniké 2023
2023-11-10 - Kvartalsrapport 2023-Q3
2023-08-23 - Kvartalsrapport 2023-Q2
2023-06-19 - Årsstämma
2023-05-16 - X-dag ordinarie utdelning ENERG 0.00 NOK
2023-05-16 - Kvartalsrapport 2023-Q1
2023-03-07 - Bokslutskommuniké 2022
2023-01-27 - Extra Bolagsstämma 2023
LandNorge
ListaEuronext Growth Oslo
SektorEnergi & Miljö
IndustriEnergikällor
Energeia är verksamt inom energisektorn. Bolagets affärsverksamhet är inriktad mot produktion och distribution av förnybar energi via solkraftverk. Produktionen sker via egna anläggningar i Europa där kunderna består av både privata kunder, samt små- och medelstora företagskunder inom varierande sektorer. Bolaget grundades 2010 och har sitt huvudkontor i Oslo, Norge.

Analysera bolaget i Börsdata!

All ägardata du vill ha finns i Holdings!

Energeia AS: Legal dispute concerning Power Purchase Agreement in the Netherlands

2026-08-11 16:58:51
Oslo, 11 August 2026


Energeia AS ("Energeia" or the "Company") announces that its subsidiary Energeia
Leeuwarden B.V. received a writ of summons on 4 August 2026 from Coöperatie NLD
Energie U.A., formerly trading under the name Energie VanOns ("EVO").
The proceedings have been brought before the District Court of the Northern
Netherlands (Rechtbank Noord-Nederland), Leeuwarden location, and concern a
dispute over the interpretation and application of the price formula in the
Power Purchase Agreement ("PPA") concluded between Energeia Leeuwarden B.V. and
EVO on 6 August 2019, as amended by addendum dated 11 September 2020.

The dispute concerns, in the main, the question of which SDE parameters
published by the government and the Netherlands Environmental Assessment Agency
(Planbureau voor de Leefomgeving, "PBL") must be applied in calculating the
price for the electricity supplied by Energeia Leeuwarden's solar park.

More specifically, the dispute concerns the question of whether periods of six
hours or longer with negative EPEX Spot prices should or should not be included
in the calculation of the relevant market price and the profile and imbalance
factor.

EVO takes the position that a negative-price-hours correction must be applied.
EVO also claims payment by Energeia Leeuwarden of a total of EUR 375,482.13
including VAT, relating to the final settlements for 2023, 2024 and 2025, plus
contractual interest and legal costs, and seeks to have this correction
methodology declared applicable to future settlements up to and including the
end of the 10-year contract term.

Energeia Leeuwarden disputes both EVO's interpretation of the agreement and the
resulting payment claims.

Energeia Leeuwarden takes the position that the settlement should be based on
the relevant SDE/PBL parameters that apply to the subsidy regime under which the
solar park falls. Under this approach, periods of six hours or longer with
negative electricity prices are not included in determining the market price of
electricity.

Energeia Leeuwarden's solar park holds an SDE decision (SDE-beschikking) dated
2017. Energeia Leeuwarden is of the view that this is relevant to determining
the applicable parameters under the PPA.

The dispute has already been the subject of discussions between the parties for
a considerable time. In October 2025, the parties made arrangements aimed at
reaching an amicable resolution. The parties ultimately did not reach a
definitive settlement, following which the dispute was submitted to the court
for adjudication.

Energeia Leeuwarden will, in consultation with its legal advisers, mount a
reasoned defence against the claims brought and defend its interpretation of the
agreement in the proceedings.

The first cause-list date (roldatum) in the proceedings has been set for 2
September 2026.


For further information, please contact:

Jarl Egil Markussen, CEO, e-mail: jarl@energeia.no and tel: +47 480 23 214

This information is subject to the disclosure requirements pursuant to section
5-12 of the Norwegian Securities Trading Act.