16:09:28 Europe / Stockholm

Kurs & Likviditet

Kursutveckling och likviditet under dagen för detta pressmeddelande

Kalender

2024-11-19 Kvartalsrapport 2024-Q3
2024-08-23 Kvartalsrapport 2024-Q2
2024-05-22 Kvartalsrapport 2024-Q1
2024-05-08 Ordinarie utdelning IWS 0.00 NOK
2024-05-07 Årsstämma 2024
2024-02-27 Bokslutskommuniké 2023
2023-11-22 Kvartalsrapport 2023-Q3
2023-08-24 Kvartalsrapport 2023-Q2
2023-05-25 Kvartalsrapport 2023-Q1
2023-05-09 Ordinarie utdelning IWS 0.00 NOK
2023-05-08 Årsstämma 2023
2023-02-28 Bokslutskommuniké 2022
2022-11-15 Kvartalsrapport 2022-Q3
2022-08-30 Kvartalsrapport 2022-Q2
2022-05-25 Kvartalsrapport 2022-Q1
2022-05-09 Årsstämma 2022
2022-04-28 Ordinarie utdelning IWS 0.00 NOK
2022-04-06 Extra Bolagsstämma 2022
2022-02-11 Bokslutskommuniké 2021

Beskrivning

LandNorge
ListaEuronext Growth Oslo
SektorEnergi & Miljö
IndustriEnergikällor
Integrated Wind Solutions är verksamma inom offshore-industrin. Bolaget levererar integrerade lösningar för vindkraftverk. Tjänsterna inkluderar design, produktion, montering, logistikinstallation till eftermarknadsservice. Utöver huvudverksamheten erbjuds även diverse mervärdestjänster som mätning och utvärdering. Störst verksamhet återfinns inom Skandinavien. Huvudkontoret ligger i Oslo, Norge.
2023-09-29 13:21:46
Integrated Wind Solutions ASA ("IWS") has, through its wholly owned subsidiary,
IWS Fleet AS, agreed with the shipyard China Merchants Industry Holdings., Ltd.
("CMI") to postpone equity yard instalments of total EUR 36m on IWS Seawalker,
IWS Starwalker, IWS Moonwalker, and IWS Sunwalker by up to one year, and thereby
strengthen the company's liquidity position.

The delivery schedules for IWS Windwalker, IWS Seawalker, and IWS Starwalker are
unchanged, while IWS Moonwalker and IWS Sunwalker are moved forward by one
month.

Furthermore, IWS Skywalker commenced its sea trials on 17 September in
preparation for delivery in the fourth quarter. The vessel will commence the
first out of three Dogger Bank (UK) contracts after delivery.

In addition, IWS is in discussions with clients for IWS Windwalker, and the
company expects to enter a charter contract prior to the delivery of the vessel.

IWS has a strong cash position and favourable debt financing in place for the
first four newbuildings.

For further information, please contact:

Lars-Henrik Røren
CEO Integrated Wind Solutions
Phone: +47 98 22 85 06
E-mail: lhr@integratedwind.com

Marius Magelie
CFO Integrated Wind Solutions
Phone: +47 920 27 419
E-mail: mm@integratedwind.com

About:
Integrated Wind Solutions ASA offers a fleet of state-of-the-art service vessels
to the offshore wind industry combined with a suite of adhering services to
reduce the levelised cost of energy ("LCOE") for offshore wind. The Company has
six Commissioning Service Operation Vessels ("CSOVs") under construction with
delivery in 2023, 2024 and 2025 in addition to options for two additional
vessels. Furthermore, IWS owns the offshore wind supply-chain service company,
IWS Services A/S and has a 30% ownership in the independent advisor,
consultancy, data intelligence and wind farm operator firm PEAK Wind Group.