17:10:19 Europe / Stockholm

Kurs & Likviditet

Kursutveckling och likviditet under dagen för detta pressmeddelande

Kalender

2024-02-29 Bokslutskommuniké 2023
2023-11-16 Kvartalsrapport 2023-Q3
2023-07-26 Kvartalsrapport 2023-Q2
2023-05-12 15-6 2023
2023-04-27 Kvartalsrapport 2023-Q1
2023-04-17 Ordinarie utdelning SEAW7 0.00 NOK
2023-04-14 Årsstämma 2023
2023-03-02 Bokslutskommuniké 2022
2022-11-17 Kvartalsrapport 2022-Q3
2022-10-06 Extra Bolagsstämma 2022
2022-07-28 Kvartalsrapport 2022-Q2
2022-04-28 Kvartalsrapport 2022-Q1
2022-04-11 Ordinarie utdelning SEAW7 0.00 NOK
2022-04-08 Årsstämma 2022
2022-03-03 Bokslutskommuniké 2021
2021-11-17 Kvartalsrapport 2021-Q3
2021-09-30 Extra Bolagsstämma 2021
2021-08-27 Kvartalsrapport 2021-Q2
2021-05-28 Kvartalsrapport 2021-Q1
2021-05-21 Ordinarie utdelning SEAW7 0.00 NOK
2021-05-20 Årsstämma 2021
2021-02-25 Bokslutskommuniké 2020
2020-11-13 Kvartalsrapport 2020-Q3

Beskrivning

LandNorge
ListaEuronext Growth Oslo
SektorTjänster
IndustriShipping & Offshore
Seaway 7 är verksamma inom transportbranschen. Bolaget är specialiserade inom hantering och transport av tyngre material. Särskilt affärsfokus återfinns inom den maritima sektorn, där bolaget erbjuder transportlösning för större projekt som sker ute till havs. Störst verksamhet återfinns inom den nordiska marknaden, där kunderna återfinns inom olje- och gassektorn. Bolaget har sitt huvudkontor i Oslo.
2022-08-08 08:00:00
Oslo - 08 August 2022 - Seaway 7 ASA is pleased to announce that it has signed a
Letter of Award with Moray Offshore Windfarm (West) Limited, to commence early
works on the Engineering, Procurement, Installation and Commissioning (EPIC) of
inter-array grid cables for the Moray West offshore wind farm.

The Moray West offshore wind farm development is located on the East coast of
Scotland in the Moray firth, approximately 22.5 km from the Caithness coastline.
The development will be comprised of 60 wind turbine generators with an
installed capacity of 882MW.

Seaway 7's scope is under final negotiation and may include the supply and
installation of approximately 125 km of 66 kV subsea power cables and respective
cable protection systems. The company will utilise vessels from its
state-of-the-art cable lay fleet which will commence work on the project in
2024. Execution of the scope will be led from Seaway 7's Aberdeen office.

The Moray West project recently obtained a Contract for Difference (CfD) as part
of the UK Government's latest CfD Allocation Round. The project is expected to
reach financial close (FC) in the coming months, with first power expected in
2024.

Once executed, Moray West will represent a sizeable (1) contract agreement. The
contract will not be recognised in Seaway 7's backlog until FC has been reached.


(1) "Sizeable" contracts are between $50m and $150m.

-Ends-


Contact for investment community enquiries:
Mark Hodgkinson
Email: ir@seaway7.com

About Seaway 7
Seaway 7 is a global leader in the delivery of fixed offshore wind
projects, committed to contributing to an efficient and sustainable energy
supply for the future.

Seaway 7 is listed on Oslo's Euronext Growth (SEAW7).

Moray West Project ownership
The Moray West project is being developed by Ocean Winds. Ocean Winds is the
result of a 50-50 joint venture between EDP Renewables (EDPR) and ENGIE for the
purpose of offshore wind deployment. Ignitis Group has a minor shareholding in
Moray West. In the United-Kingdom Ocean Winds is also the majority shareholder
of Moray East, Scotland's largest offshore wind farm. Ocean Winds has recently
been awarded exclusive rights by Crown Estate Scotland to develop a bottom-fixed
offshore wind project targeting 2 GW, now named Caledonia, adjacent to the
existing Moray East and Moray West seabed lease area.